Standard Costing and Variance Analysis, With Real Numbers

On this page
  • The standard
  • What actually happened
  • Material variances
  • Labour variances
  • Overhead variances
  • The reconciliation
  • The question each variance answers
  • Reading this month honestly
  • Where standard costing stops being useful
  • Where this fits

A variance is the difference between what something should have cost and what it did cost. Splitting that difference into its causes is the entire point, because a total overspend of ₹1,66,900 tells you nothing you can act on, while knowing that ₹64,000 of it came from paying more for material and ₹50,000 from using more of it sends you to two different people.

Here is one month, worked all the way through.

The standard

A workshop sets a standard cost per unit before the month starts:

ElementStandard₹ per unit
Material4 kg at ₹250/kg1,000
Labour3 hours at ₹180/hour540
Variable overhead3 hours at ₹90/hour270
Fixed overhead3 hours at ₹120/hour360
Standard cost per unit2,170

Budgeted output is 1,000 units, so budgeted fixed overhead is ₹3,60,000 absorbed over 3,000 standard hours.

What actually happened

  • Actual output: 950 units
  • Material purchased and used: 4,000 kg costing ₹10,64,000, an actual rate of ₹266/kg
  • Labour: 2,800 hours costing ₹5,26,400, an actual rate of ₹188/hour
  • Variable overhead: ₹2,66,000
  • Fixed overhead: ₹3,72,000

Standard cost of actual output is 950 × ₹2,170 = ₹20,61,500. Actual cost is ₹22,28,400. The total adverse variance is ₹1,66,900. Now split it.

Material variances

Standard quantity for actual output = 950 × 4 kg = 3,800 kg.

Price variance = (standard rate − actual rate) × actual quantity
= (₹250 − ₹266) × 4,000 = ₹64,000 adverse

Usage variance = (standard quantity − actual quantity) × standard rate
= (3,800 − 4,000) × ₹250 = ₹50,000 adverse

Total material variance ₹1,14,000 adverse. Check: standard ₹9,50,000 against actual ₹10,64,000. Agrees.

Note the convention. Price variance is valued at actual quantity, usage at standard rate. That is deliberate: it stops a price problem and a usage problem from contaminating each other, so each number can be owned by the person who can affect it.

Labour variances

Standard hours for actual output = 950 × 3 = 2,850 hours.

Rate variance = (₹180 − ₹188) × 2,800 = ₹22,400 adverse
Efficiency variance = (2,850 − 2,800) × ₹180 = ₹9,000 favourable

Total labour variance ₹13,400 adverse against a standard of ₹5,13,000 and actual of ₹5,26,400.

This pairing is the most informative in the whole analysis. The workshop paid above standard and got more done per hour. That is the signature of using more experienced or better-paid people, and it may well have been the right call.

Overhead variances

Variable overhead. Standard for actual output is 2,850 × ₹90 = ₹2,56,500; actual ₹2,66,000, so ₹9,500 adverse. Split it:

  • Expenditure variance = (2,800 × ₹90) − ₹2,66,000 = ₹14,000 adverse
  • Efficiency variance = (2,850 − 2,800) × ₹90 = ₹4,500 favourable

Fixed overhead. Absorbed is 2,850 × ₹120 = ₹3,42,000; actual ₹3,72,000, so ₹30,000 adverse. Split it:

  • Expenditure variance = ₹3,60,000 budget − ₹3,72,000 actual = ₹12,000 adverse
  • Volume variance = (2,850 − 3,000) × ₹120 = ₹18,000 adverse

The volume variance is the one people misread. It is not an overspend. It says the workshop made 950 units instead of 1,000, so ₹18,000 of fixed cost found no product to attach itself to. The cost was always going to be incurred.

The reconciliation

Variance₹Direction
Material price64,000Adverse
Material usage50,000Adverse
Labour rate22,400Adverse
Labour efficiency9,000Favourable
Variable overhead expenditure14,000Adverse
Variable overhead efficiency4,500Favourable
Fixed overhead expenditure12,000Adverse
Fixed overhead volume18,000Adverse
Net1,66,900Adverse

It ties back to the total. If yours does not, the error is nearly always in which quantity a variance was valued at.

The question each variance answers

VarianceQuestionUsually owned by
Material priceDid we buy well?Purchasing
Material usageDid we waste?Production
Labour rateWho did the work?HR and production planning
Labour efficiencyHow fast did they work?Production
Overhead expenditureDid we overspend on support costs?Department heads
Fixed overhead volumeDid we make enough to absorb our fixed base?Sales and planning

Reading this month honestly

The largest single number is material price at ₹64,000 adverse, a 6.4% overspend on rate. Before treating that as a purchasing failure, the obvious question is whether the market moved. A variance against a standard set three months ago may be measuring the standard rather than the buyer.

Material usage at ₹50,000 adverse is the more actionable one. 4,000 kg consumed against 3,800 standard is 5.3% more material per unit, and that is waste, rework, or a standard that no longer reflects the process.

The interesting pairing is labour: paying 4.4% above rate and finishing 50 hours early. If those better-paid people also caused less material waste, the ₹22,400 was well spent. If material usage worsened at the same time, it was not. Variances are most useful read against each other rather than one at a time.

Where standard costing stops being useful

It assumes a repeatable process and a stable standard. In a job shop where every order differs, or where input prices move weekly, variances measure the staleness of the standard more than the performance of the month.

Revise standards deliberately and on a known cycle. A standard nobody believes produces variances nobody investigates, which is worse than not computing them.

Where this fits

General educational information. Figures are illustrative and follow from the stated standard and actuals.